What does a vault privy cost in Island Park, Idaho?
The cost table
| Item | Amount | Basis | Source + date |
|---|---|---|---|
| Tank-only & vault privy permit | $450 | per permit | EIPH Septic Permit Information Sheet, rev. 10/2024, retrieved 2026-08-12 |
| Speculative site evaluation | $450 | per evaluation; credits toward a permit within 1 year | EIPH fee schedule, effective 2026-02-02 |
| The vault unit | bid | per unit — approved septic tank (TGM §5.2) or vault toilet (§5.10) | DEQ Technical Guidance Manual §4.29, December 2025, retrieved 21 October 2026 |
| Pumping | quoted per job | tank size, access, haul — no local rate card exists | none found in our sources; national guides cluster low-to-mid hundreds |
| Permit amendment, if the plan changes | $450 | per amendment | EIPH environmental health fee table, effective 05/01/26, retrieved 5 October 2026 |
What moves the number
- Toilet count. "The volume of the vault tank must be 375 gallons for each toilet, except that no tank may be less than 500 gallons." One seat means at least 500 gallons; two seats, 750.
- Ground that rejects a pit. Lots with seasonal high groundwater, shallow rock, or fast-draining gravels are exactly where the sealed vault is the option — the ground, not the budget, chooses the system.
- Truck access. The rules require the privy "accessible for maintenance," with a secured pumping port outside the building; a pad a truck cannot reach year-round costs more every visit.
- Siting. "Vault privies should not be located in floodways" — moving the pad at design time is cheaper than moving it after the concrete.
Local fees and permits
Who sets the fee, and on what authority: EIPH's Board of Health, "under the authority granted by Idaho Code 39-414 (1), 39-414 (11), 39-416, and Administrative Rules IDAPA 41.02.01, sets the following fee schedules based upon the actual cost of providing the services."
One wrinkle before you pay anything: EIPH's fees web page labels the environmental services schedule effective 2/2/26 while the fee table PDF prints Effective 05/01/26 — read the date off the document you are holding, and re-check the table before budgeting.
And the boundary rule that can erase the whole line item: "Structures on the property served by water under pressure must install a subsurface sewage disposal system." (DEQ TGM §4.17.2, December 2025, retrieved 16 October 2026.) A vault privy serves the unplumbed lot; the day pressurized water arrives, a system — not a privy — is the plan.
How to get a real number
- If the lot is unplanned, buy the $450 speculative site evaluation first — it credits toward the permit within a year and tells you whether the ground rejects a pit.
- Bid the vault as a real tank: "a modified septic tank with inlet and outlet openings sealed or a preapproved vault unit" — those are the two forms the rule accepts.
- Book the service, not just the install: "The vault must be pumped by an Idaho-permitted septic tank pumper," on a schedule, hauling to an approved disposal site.
- Sorting call: (208) 656-1467.
Common questions
Is there a published price for the vault itself?
No — it is bid. What is published is the requirement: an approved septic tank or vault toilet unit, watertight and built of durable materials.
How big does the vault have to be?
375 gallons per toilet, with a 500-gallon floor — two seats means 750. Tank size is one of the three things a pumping quote prices.
What does the permit cost?
$450 on the tank-only and vault privy track, per the EIPH application packet retrieved 2026-08-12 — same health district, a different row than the $900 individual system permit.
What does pumping cost?
Locally it is quoted per job — tank size, access, haul — and no Island Park pumper posts a rate card. National guides cluster residential visits in the low-to-mid hundreds: an advertised average, not a quote.
Is a vault privy cheaper than a pit privy?
The pit-privy permit fee is not in the fee rows quoted here, so that comparison is a desk question at the health district. What the sources do show: the vault exists for ground a pit cannot safely serve.
What if I add running water later?
The privy stops being the plan — structures served by pressurized water must install a subsurface sewage disposal system, and that work runs through the same Eastern Idaho Public Health permitting.
Where to read next: what a vault privy is, the outhouse permit rules, the EIPH fees nobody lists, and the Fremont County permit walkthrough. Sorting call: (208) 656-1467.