How do you connect a cabin to the Island Park sewer system?
In five steps: confirm which system serves the lot, check the 500-foot rule, apply for the building permit, pay the $7,458 hook-up at the Fremont County Treasurer's Office before the permit issues, then close out the old septic tank. The one deadline that bites: the fee is due before the building permit.
The steps, in filing order
1. Find out which side of the sewer boundary the lot sits on
Parts of Island Park — including the Mack's Inn and Last Chance/Pond's areas — are served by community sewer systems, and where sewer is available to a building you connect to it rather than installing septic. The county's Island Park Sewer System page posts the connection fee; for parcel-level questions, the EIPH application packet points Fremont County applicants to Planning & Zoning at (208) 624-4643. Cost of this step: a phone call. Make it before any septic money is spent — a $450 speculative site evaluation is wasted on a lot the county will not let put in septic.
2. Check the 500-foot rule
Fremont County's Development Code requires connection, and payment of all associated fees, for any residence or application within 500 feet of an existing central wastewater treatment system — 2011 Edition, Ordinance 2011-04, section 5.35.030, retrieved 19 August 2026. One gap to ask about in exactly these terms: the code does not say how the distance is measured — from the dwelling, the parcel boundary, or the nearest point of the system. For subdivisions the reach scales with the lot count: "Connection to a central wastewater treatment system may be required where the total number of proposed lots multiplied by 200 feet would reach a collection or transmission line of an existing centralized treatment system, not to exceed one (1) mile (5,280 feet)." The when-the-county-can-require-it page works that formula out in full.
3. Apply for the building permit
The connection fee is tied to the building permit by the county's own checklist, and the order inside the sentence is the order at the counter:
"…a hook up fee of $7,458.00 must be paid prior to receiving your building permit. These fees must be paid at the Fremont County Treasurer's Office after applying for the building permit."
— Fremont County Pre-Construction Check List for Building Permits, revised 2026-04-17
Apply first, pay second, receive the permit third. Arriving at the Treasurer's window before the application exists is the sequencing error the checklist is written against.
4. Pay the $7,458 hook-up fee at the Treasurer's Office
| Amount | What it is | Source and date |
|---|---|---|
| $7,458 | Connection fee where the Island Park/Mack's or Last Chance/Pond's system serves the building | Fremont County pre-construction checklist, revised 2026-04-17; the county's Island Park Sewer System page, retrieved August 2026 |
| $450 | EIPH speculative site evaluation — only if step 1 lands the lot on the septic side | EIPH fee schedule, effective 2026-02-02 |
The checklist names the Fremont County Treasurer's Office as the payment point; it prints no phone number, and this site has none on record — ask the county, starting with Planning & Zoning at (208) 624-4643. What the fee does not cover: the plumbing from the building to the line, which is private bid work like any other construction here. The full cost picture is on the cost page.
5. Close out the old septic tank
Connecting to sewer diverts the flow, and under Idaho's rules a system that no longer receives wastewater is abandoned — with a three-step duty on the property owner: disconnect the inlet and outlet piping, pump the scum and septage with approved disposal, then fill the tank with earthen materials, destroy it, or remove it from the ground (IDAPA 58.01.03 §007.22, as amended 1 July 2025, retrieved 7 September 2026). The pumping step is permitted-pumper work, and the completed abandonment belongs in the health district's file for the parcel. The full walkthrough — triggers, endings, paperwork — is on the abandonment page.
Where this goes wrong
- Septic design money spent on a sewer-served lot. Confirm the boundary before paying for an evaluation, a design, or a permit — the connection requirement is not waived because a septic plan already exists.
- The fee arrives at the wrong moment. It is paid after applying for the building permit and before receiving it; budget it as a pre-permit cost, not a closing cost.
- The distance question never gets asked. The code does not define where the 500 feet runs from — get the county's answer for your parcel in writing before relying on being outside it.
- The old tank is forgotten. A full tank left in the ground after connection is both a contamination path and a collapse hazard, and the abandonment duty is the property owner's by name.
- Two instruments, one lot. The Development Code's distance rules and a sewer district's own mandatory-connection ordinance are separate instruments — a parcel can be caught by either.
What we handle, what you file
You or your builder files the building-permit application and pays the Treasurer; a permitted pumper and an excavator close out the old tank. The sorting call — which side of the boundary your lot sits on, and what the old system's file says — is free: (208) 656-1467.
Common questions
How much does it cost to connect to the Island Park sewer system?
$7,458 — the 2026 connection fee where the Island Park/Mack's or Last Chance/Pond's community system serves the building, paid at the Fremont County Treasurer's Office before the building permit issues. Plumbing to the line is a separate private bid.
How do I know whether my lot is in a served area?
The Mack's Inn and Last Chance/Pond's areas are the named served pockets. Confirm at the parcel level with Fremont County Planning & Zoning, (208) 624-4643 — the office the EIPH application packet itself points Fremont County applicants to.
Does the 500-foot rule mean I have to connect?
If the lot is within 500 feet of an existing central wastewater treatment system, the Development Code requires connection and payment of all associated fees. How the 500 feet is measured is not defined in the code — ask about your parcel specifically.
Do I have to abandon my septic tank when I connect?
Yes. Connection diverts the flow, which makes the old system abandoned under the rule, and the three-step abandonment — disconnect, pump, fill or destroy or remove — is the property owner's responsibility.
Can I keep the septic system and skip the connection fee?
Not where the code requires connection — inside 500 feet of an existing central system, or where a subdivision's lot count reaches a line under the 200-feet-per-lot formula capped at one mile.
Who do I call — the county or the health district?
The county for the boundary question, the building permit and the Treasurer payment; Eastern Idaho Public Health for the old system's records and its abandonment. The steps above say which office answers which.
Call (208) 656-1467 · Text the line